Foundry

We have 2 stages of inspection in our foundry.

1. INSPECTION BEFORE SHOT BLASTING.

A) DECORING OF MOULDS.
B) KNOCK OUT OF RUNNERS & RISERS.
C) HEAT WISE HARDNESS CHECKING OF EACH BATCH BY POLDI HARDNESS TESTER.
D) VISUAL INSPECTION FOR CRACK OR ANY OTHER FOUNDRY DEFECTS.
E) O.K. PIECES SEND FOR SHOT BLASTING

Ami Allowys | Ahmedabad

2. INSPECTION AFTER SHOT BLASTING.

A) VISUAL INSPECTION BEFORE FETTLING.
B) CRITICAL WALL THICKNESS CHECKING BY DIAL CALLIPER
C) CHIPPING AND GRINDING BY CONVENTIONAL METHOD.
D) FUBAK UBSOECTUIB IF CHIPPING, GRINDING & ANY DEFECTS BEFORE Zn – Cr PRIMER BY DIPPING.
E) MICROSTRUCTURE (RANDOM CHECKING)

Ami Allowys | Ahmedabad

Foundry related test Reports

  • We provide foundry test reports as per A 3.1 EN 10204 Certificate of compliance to a standard for the material, with every batch of casting poured.
  • We provide casting dimensional test report for first article inspection.

Machine Shop

We have 3 stages of inspection in our machine shop similar to the foundry.

1) Incoming inspection

We inspect 100% incoming raw and machined components that enter our machine shop to confirm the following parameters:

Visual defects in raw castings before starting the machining process.
If machining is outsourced or pre-machined the dimensions are checked 100% before moving the component for further processing.
Assembly child part inspection is done according to the control plan for frequency and specifications of the particular child part.

2) In process inspection

We do inspect the processes every batch for the process related errors like GD&T. First component is checked for dimensional variation after every setup change on each machine or process or machining. If in doubt we also verify the components for critical parameters like GD&T using external CMM facility.

3) Final inspection

Final inspection is carried for components according to the inspection frequency of the particular component as per control plan like:

Dimensional accuracy with respect to drawing.
Hydro testing of the pressure rated component as per maximum working pressure for 100 % of the components.
Inspection of visual defects, foundry related defects, dents, chatter marks etc. is carried out before the components move for dispatch crossing the inspection fire wall.
Assembly inspection for, hydro testing, assembly working inspection etc.
Packing inspection is done for all the packages leaving the warehouse for any defects related to the packaging for Exports or domestic shipments.
Pre-Dispatch inspection is done to check all the related technical and commercial documents are provided before the shipments leaves the warehouse as per the instruction in purchase order.

Machine shop related test reports
  • Dimensional inspection reports of components according to the inspection frequency of control plan.
  • Hydro test report as component pressure rating.
  • Assembly inspection report as per assembly drawing requirement.
  • CMM reports for GD&T for first article inspection or if there is change in machining process.